Mangla Dam Upgradation Project (under supervision of General Electric - G.E)
Qadbros is proud to be a partner of G.E in the Mangla Dam upgradation project wherein capacity enhancement of each turbine, from 100 MW to 135 MW, is being undertaken.
Some of the works performed by Qadbros include casting of MIV Bearing Carrier, refurbishment of 100 MW Turbine Housings, Outer & Inner Head Covers, Bearings, Irrigation Valve Body & Sleeve, Generator Thrust Pad, Operating Ring & Slip Ring & Exciter Shaft. Major scope covered includes:
- Casting of parts as per required quality standards including Radiographic Testing
- Ultrasonic and Magnetic Particle Testing for Identification of defects
- Weld repairing of defects in compliance to referred standards
- Machining to achieve original dimensions